Loyalty Juggernaut
🏢
9
Active Clients
⚠️
5
Require Attention
📅
2
Due This Week
0
On Track
⏸️
8
On Hold
⚠ Leadership Attention 9 clients · sorted by priority
Filtered to action required — showing 5 of 9 clients. Monitor and on-track hidden.
Deutsche Telekom
AI TRANSLATE CALL THIS WEEK · DATE NOT FIXED
  • 🌐 AI Translate — DT Call This Week, Date Not Yet Fixed: Use case and next steps discussion with the DT team. DT's initial feedback: reverse-direction translation (local languages → English) would be more useful than the existing one-way flow only. Aug 11 AI SoS (Monika): feedback discussions \"were pending due to the World Cup period but are now resuming.\" DT has not yet shared their expectations / updated requirements — treat the call as scoping, not a requirement review. No date confirmed — slot still to be agreed with DT. Detail contact: Vishnu Sankar.
  • AI Compass — On Hold (POC Complete): Use Case Review call held Jul 21 ✓ — 8+ use cases reviewed (banner AI sourcing, sponsor/offer creation from contracts, consolidated reporting, brand categorization, acquisition channel distinction). Compass was scoped as a proof of concept — POC complete, no further next steps planned for now.
  • AI Sense: Commercials shared Jul 7. Nereida moving out of Magenta Moments — Monika reached out to Arindam Nath Jul 20 asking for time to connect. Summer vacations causing delays. Awaiting Arindam's availability.
↗ Latest from Email · Jira
Transcript (Jul 21, 58 min): Use Case Review call completed with Vaso/Mia/Mikus/Petra/Fawaz (DT/IDEA) + LJI team. 8+ Compass use cases covered: banner AI sourcing, sponsor/offer creation from contracts (~15 new sponsors/country/month), consolidated QS reporting (Vishnu to explore custom report), brand categorization Hero/A/B/C (Vaso to share IPC criteria), acquisition channel distinction CZ (IDEA vs iNFIX). LJI: expose custom attributes + DT glossary as eng priorities. CDL call to be scheduled (clicks/impressions). Pending DT: time-savings data + criteria doc. No timeline commitments. · Jul 20: Monika reached out to Arindam Nath (new DT AI Sense contact). · AT-3 (Jul 13): Nereida moving out of Magenta Moments.
Emirates
SEPT 2 DEMO — 8 DAYS · AI INDIVIDUALIZE SIGNED OFF
  • 🎬 Sept 2 — Agentic Journey Demo to Dr. Najjib (8 days out): Hard, negotiated date — EK originally asked for one week; "the maximum time we could buy till 2nd of September" (AI SoS Aug 11). Build is live: 215-compass deployed to UAT (Aug 19, Brain Trust integrated), app v2217 on TestFlight (Aug 21), opt-in flow UI + backend complete (Aug 24). Partner coverage 25 scraped → 95 confirmed URLs → ~200+ processing — dev not blocked by sponsor data. Guardrails: MVP stays member-initiated only, temporary UX explicitly labelled as temporary, no scope committed until Kalpak approves wireframes. Open blocker: Octa JWT vs Gravity JWT auth mismatch (Aug 20, unresolved). Internal Agentic Journey MVP Demo rehearsal Thu Aug 27, 5:00–5:45 PM IST (Teams, organised by Kapileswar) ahead of the client demo.
  • ⚠ Privilege Code Duplication — ~12–15K Members Affected (Aug 24): System caps at an upper threshold of 256, causing duplicate privilege codes. Kalpak directed it be run as a separate serialised track from AI adoption so it does not delay go-live. Proposed long-term fix is more digits in the code — pending client confirmation that downstream systems can absorb it.
  • ✅ AI Individualize — ALI SIGNED OFF (Aug 24), Moving to PROD Closed Group: Aug 20: Aakriti Bhat sent Ali the AI-Individualised Offer and notification configuration document plus SWED app / GRAVTY® UAT testing evidence and the UAT handback file. Aug 21: chased for sign-off. Aug 24, Ali Lootah: "The build looks good overall. The Activations team will share a few copy updates, but from our side, we are happy to proceed with the closed-group testing." LJI replied same day: PROD Closed Group setup being initiated; copy changes for PROD go-live awaited from Activations. Prior state (now superseded): Reward structure (2X / 25% Luxury) simulated on Jun handback — 35,446 members, 1.87M incremental bonus miles, 53% of 3.5M budget ceiling. Simulation results shared back with Ali Lootah — awaiting his confirmation to proceed. Jul 30 internal build sanity: CTA added to offer cards ("Click here to know the partner"); dynamic offer subtitles proposed; category icons fully configurable — reward structure rules still pending Ali's confirmation.
  • Agentic AI NL Search — Demo to Emirates Aug 5, Strongly Received: Anita and team ran their own unrehearsed prompts; output was relevant, not pre-engineered. "The reception was really good" — better than EK expected for a first iteration. EK asks: (1) make experience miles-centric not just partner search; (2) offer opt-in inside the chat journey (opt-in is mandatory to earn on EK offers); (3) softer LLM tone on no-match results. Steering committee demo requested ASAP + broader EK team hands-on testing.
  • Next for NL Search: Move from dev-tenant app to a controlled beta selected EK users interact with directly — polished UX explicitly not required. LJI assessing the route into the Emirates test environment. Dependency on Ali: sponsor URL sheet to be completed from serial 31 onward (1–30 done) — prototype covers only ~25 sponsors today. Offer data also needs base-vs-promotional context so the agent can explain a "3X Miles" offer properly.
  • 🚀 Infinity — Proposal Held Pending Alignment Call (AT-164 / AT-171): Scope work complete — approach shaped across mobilisation, delivery construct, resourcing and commercials. LJI has deliberately not sent the proposal, requesting 30 minutes first to align on three points that materially shape it: (1) how much budgetary visibility Emirates needs at this stage, (2) expected timeline/urgency, (3) the most pragmatic route into initial discovery and scoping. Rationale: avoid an indicative construct that changes materially once priority scope is defined. Slot proposed for 3:00–3:30 PM Dubai on Aug 17 — no confirmation from Chris Gale recorded as of Aug 25 (8 days).
  • 📨 Infinity — Discovery Proposal Sent Aug 21, Awaiting Chris Gale: The Aug 17 alignment call went ahead. Recap same day: (1) discovery-led mobilisation — priority is not to prematurely estimate or resource the full MVP but to run a focused discovery covering priority MVP scope, technology/application approach, reuse of existing GRAVTY®/SWED capability versus extension or new build, UX, dependencies and Emirates stakeholders; (2) outcomes to cover prioritised scope, integration approach, capability fit-gap, dependencies, sequencing and resource/budget requirements; (3) LJI to send a discovery proposal by EOD Wednesday (Aug 19). That date slipped — Aug 19: "we need a couple of more days to finalise the proposal. Does it work if we get back to you by Friday?" Proposal was then sent Friday Aug 21: a focused four-week Discovery & Scoping engagement with a lean team construct, working cadence, required Emirates inputs and commercial outline, concluding in three outputs — an agreed Scope of Work, a confirmed mobile technology direction, and a defined Build-phase plan and commercial proposal. Structured so delivery commitment scales progressively once scope and dependencies are validated. No reply from Chris Gale recorded as of Aug 25 (2 working days). Superseded watch item: The Aug 11 commitment was to share the plan "by the end of this week" (Fri Aug 15). Emirates has not received a document, so from Chris's side this reads as a missed date regardless of the reasoning — unless the alignment call lands and resets expectations explicitly — it has not been held as of Aug 25. Same-day request with ~5 hours' notice. It has now slipped 8 days with nothing formal sent and no reply logged — and attention has since shifted to the Sept 2 demo. All six analysis sub-tasks (AT-165–170) remain To Do in Jira.
↗ Latest from Email · SoS · Jira
Email (Aug 11, Chris Gale → Kapileswar): "Thanks very much for the details and proposed structure - sounds great. Lets connect early next week to go through it." · Email (Aug 17, Kapileswar → Chris Gale): scope work complete, approach shaped across mobilisation, delivery construct, resourcing and commercials — proposal deliberately held pending a 30-min alignment call on budgetary visibility, timeline/urgency and discovery approach. Slot requested 3:00–3:30 PM Dubai on Aug 17; no confirmation from Chris recorded as of Aug 25. · Contact Report (Aug 11, Kapileswar → Ali, Anita, Rashed): AI Individualize offer-entry experience to match the specific treatment, not one generic screen; no additional mobile-app dev for initial launch; UAT plan agreed once handback feedback and offer screens close. Agentic AI directions: miles-centric value articulation (needs base-vs-promotional offer context), in-chat opt-in journey — discover → offer → explain Miles → opt in → T&Cs → guide to location, softer fallback routing to Miles Mall, and a controlled beta. Ali to complete sponsor URL sheet from serial 31 and provide an EK drive location for the recorded demo. · Aug 5 SoS: demo "taken quite positively… the reception was really good". · Aug 7 SoS: test segment cut to 1,000–2,000 members to control LLM prediction costs. · Aug 4 SoS: Gemini API switched to OpenAI.
Jumeirah
AI-SCAN ON HOLD · AGENTIC MVP PROPOSED
  • AI Recommend: Live on Prod. Sep go-live target for Experiences model. Aug 5 triage: of the client's feedback items, 5 are addressable via QuickSight reporting; the remaining 3–4 need development — POC started, results next day. No PRD is coming from the client, so LJI is writing the requirements doc itself (Kapileswar, committed end of week). Aug 4: propensity scores confirmed for UI display at go-live, model explainability deferred to a later roadmap item.
  • AI Pulsar: Weekly/fortnightly updates to Jumeirah ongoing. GRAVTY® 2.15.0 deployed on Jumeirah UAT (AT-8, Aug 11) — client informed, Jumeirah team now testing from their end.
  • Agentic AI MVP: Art of the Possible workshop proposed to Candida Goradia + Lucy Wilson (Jul 27 email) — no response yet.
  • AI-Scan: Placed on hold by Candy (Jul 24) — Jumeirah One transformation is moving away from points-based programme; this feature will be phased out, so investment not commercially justified. Kapileswar acknowledged. Formally moved to On Hold in Jira (AT-112, Aug 11) — "requirement on hold as their priority is to focus on delivering the MVP scope." Door open if requirements change.
↗ Latest from Email · Jira · Meeting Tracker
Aug 5 SoS: AI Recommend feedback triaged — 5 items addressable via QuickSight reporting, remaining 3–4 need development; POC started with results due next day. No PRD coming from client, so LJI is authoring the requirements doc itself — Kapileswar committed to end of week under pressure to move fast. Aug 4 SoS: propensity scores confirmed for UI display at go-live; model explainability deferred. Jumeirah filtering implementation paused pending clarified requirements + UX wireframes. Aug 3 SoS: redemption offer filtering — Django-side vs AI model adjustment still under evaluation. · Email (Jul 24, Candy → Kapileswar): AI-Scan placed on hold — Jumeirah One transformation moving away from points-based programme. · Email (Jul 27, Kapileswar → Candida + Lucy Wilson): Art of the Possible workshop proposed for Agentic AI MVP — awaiting response. · AT-8 (Aug 11, Risheek Kaul): "Deployed on UAT - communicated to client, Jumeirah team to test from their end."
Global Hotel Alliance
OPEN DECISION
  • AI Trust: High Value Accrual Hold on track for GRAVTY® 2.15.1 (July).
  • Compass Audit Logs (Ph.2): DevInt OK ✓ — All issues closed Jul 10. Security and API labels added. Story moved to DevInt OK.
  • AI-Scan (Ph.1): Scoped — blocked on GHA confirming eligibility/category mapping.
  • Agentic AI (New Scope): EKA-style use cases — Jul 30 (Monday.com): Kapileswar to connect with Dinesh/Varun for EKA use case clarity before progressing.
  • AI-Scan Earn & Dine (New Scope): Non-integrated discovery (restaurants, gyms, POS) — Jul 30 (Monday.com): Kapileswar to drop follow-up with Sri.
↗ Latest from Monday.com · Jira · Meeting Tracker
Monday.com (Jul 30): (1) Agentic AI — Kapileswar to connect with Dinesh/Varun for EKA use case clarity. (2) AI-Scan Earn & Dine — Kapileswar to drop follow-up with Sri. · BL-123271 (Jul 10): Compass Audit Logs Ph.2 — DevInt OK, all issues closed. · AT-52 (Jun 17): AI Trust — High Value Accrual Hold confirmed for GRAVTY® 2.15.1. · AT-53: D$ Transfer Pattern Anomaly — deterministic controls framework ready, awaiting GHA revert.
Liverpool
COMMERCIAL SENT
  • AI Individualize (MVP): Personalised offers — upsell, cross-sell, frequency. 6 use cases in Discovery (AT-132–AT-137).
  • AI Recommend (Fast Follow): Next Best Offer in coupon carousel — To Do.
  • Commercial: Sent to Liverpool — awaiting client revert on terms. 9 AI module stories scoped (AT-122), 7 future-phase modules in backlog.
↗ Latest from Jira
AT-123 (AI Individualize): In Tracking Sprint — 6 use cases (AT-132–AT-137) now in Discovery. · AT-124 (AI Recommend): In Tracking Sprint — To Do. · AT-125–AT-131: Moved to backlog (7 future-phase modules). · AT-122: Epic active. Commercial sent — awaiting Liverpool team revert on terms.
Sunrise GmbH
REQUIREMENTS IN · FEASIBILITY REVIEW
  • AI Recommend — Newsletter Personalisation (Aug 6 demo call): Personalise newsletter offers for ~1.2M Sunrise customers, ranking ~1,000 existing live offers into three buckets (last redemption category / strongest interest category / max points price cap). No new offer creation required.
  • Delivery model: API-consumed, weekly or bi-weekly batch scoring — real-time not required in phase 1. POC on a production member subset with defined KPIs before rollout. Target go-live: early 2027.
  • Gating item: Requirement doc with Harsh & Mohiddin for feasibility check (AT-157) — timeline and implementation cannot be committed to the client until this clears.
↗ Latest from Jira · Demo Call
AT-155 (Sunrise Epic) created Aug 10 with AI Recommend story (AT-156) and 7 subtasks: feasibility assessment (AT-157), propensity ranking (AT-158), three-bucket selection logic (AT-159), business rules & eligibility filtering (AT-160), recommendation API (AT-161), batch scoring job (AT-162), POC & KPI definition (AT-163). · Aug 6 demo call: full requirement captured — 1.2M members, ~1,000 live offers, three-bucket selection, API + scheduled batch scoring, POC before rollout, early-2027 go-live. Reverse use case (best members for a given offer) raised as secondary — not currently supported by AI Recommend, scoped out of phase 1. · Aug 6 AI SoS: AI Recommend newsletter formally adopted as a batch-mode solution.
Shoppers Stop
AI SEQUENCED · DISCOVERY DECISIONS OPEN
  • Sequencing settled (Aug 11): First priority is the end-to-end coupon management and fulfilment execution layer — coupon constructs, orchestration through GRAVTY®, POS/online validation, and consumption/status feedback to close the data loop. Required regardless of whether targeting ends up cohort-led, rule-based or AI-personalised. Led by Kushagra Rastogi.
  • AI Individualize deferred, not deprioritised (AT-173): Resumes once the execution foundation matures, moving progressively from cohort-/rule-led treatments towards member-level decisioning.
  • 6 discovery decisions block the AI track (AT-174–179): Phase 1 objective · first controlled experiment scope · what AI decides per member vs business rules · coupon universe · earn-and-consume mechanic · success measure. All need one session with business/loyalty/campaign stakeholders — not yet scheduled.
  • Client position (Jyotsna Lal, Aug 10): wants the full existing GRAVTY® configuration set enabled from day one — targeting by category/brand/bill value selectable at campaign time — even if piloted on smaller samples. Accepts AI learning is an ongoing process.
↗ Latest from Email · Jira
Email (Aug 11, Kapileswar → Jyotsna Lal): "we were able to close the loop on the sequencing and are now aligned on the immediate priority" — execution layer first, AI-driven offer personalisation "remains an important subsequent layer, rather than being deprioritised." · Email (Aug 10, Jyotsna Lal): split the ask into enabling existing GRAVTY® functionality versus AI learning and optimisation; POS integration underway, wants capabilities available day one. · Email (Aug 7, Kapileswar): proposed six decisions to define the first executable use case, recommending an iterative build starting with one representative Phase 1 use case rather than operationalising all objectives simultaneously. · Jira: AT-172 epic created with AI Individualize story (AT-173) and 6 discovery sub-tasks (AT-174–179).
Mashreq Bank
DESIGN ANALYSIS REQUIRED
  • AI Trust / Approval Workflow (BL-127491): Maker-checker story at Ideate stage — not yet to PSG. Engine team (Rahul Allu, Jul 8) looking at decoupling static rules from AI Trust.
  • Architecture Decision: Standalone vs. AI Trust integration — unresolved, pending design analysis. 3 sub-tasks created: Tech Design Doc, QA Review, Test Plan — all To Do.
↗ Jira · BL-127491 · Jul 8, 2026
BL-127491 ("Ability to setup an Approval Workflow (Maker-Checker) for Points Adjustment Service") — Status: Ideate. Assignee: Rahul Allu. Jul 8 (Srivalli): "Where are the PSG comments?" · Jul 8 (Rahul): "We haven't taken this to PSG yet. Engine team is looking at the possibility of decoupling static rules from AI Trust." · Sub-tasks created: BL-127492 (Review), BL-127493 (Test Plan), BL-127494 (Tech Design Doc) — all To Do.
WestJet
CLIENT PUSHBACK · SEARCH + SIMULATION
  • ⚠ Client Unhappy with Search Solution (Aug 21): WestJet is not accepting a search-screen solution proposed roughly two months ago, which loaded all flights for a single bid. Azeem to sync with Ishwar on scalability and ancillary mapping, and consult Nishant on the specific points of dissatisfaction.
  • ⚠ Bonus Offer Simulation Rejected (Aug 21): Client is not accepting the proposed rate-return approach and insists on full simulation within the system, despite the complexity of per-member calculations and exclusions.
  • Flight Search Load + Promotional Rules (Aug 20): WestJet requires 15 API calls for a single flight search due to multiple segments and fare classes. Promotional rules are applied at segment level, not flight level. Async integration approach to be finalised with the vested team's solution architect.
  • GDPR — Transaction Deletion (Aug 20): Handling of transaction data on member deletion is unresolved. Being validated with product whether transactions should be hidden rather than deleted; if treated as an enhancement, a story is to be raised for the AI team.
  • AI Trust / Fraud Scoring: Day 1 health confirmed — 127 BITs processed, 50 sampled, all correct, fraud scores low. Rollout itself remains stable.
  • Evaluation & Retraining (AT-110): 3 reports delivered to WestJet (Jun 22 – Jul 8). New models trained and deployed on client-labelled data. Model metrics comparison (old vs new) shared with WestJet. AT-111 (Optimization & Retraining) next.
↗ Latest from AI SoS · Jira
AI SoS Aug 21 (Azeem): client unhappy with the search screen solution proposed two months prior; not accepting the rate-return approach for bonus offers and insisting on full in-system simulation. · AI SoS Aug 20 (Nikitha, Smit): 15 API calls per flight search; promotional rules applied at segment level; GDPR transaction-deletion handling to be validated with product. · AT-32 (Jul 17, Mohiddin): 3 reports delivered to WestJet (Jun 22 – Jul 8). New models trained and deployed on client-labelled data. Model metrics comparison (old vs new models) shared with WestJet. · AT-110 (Reporting & Evaluation): In Progress. AT-111 (Optimization & Retraining): To Do.
📅 Upcoming Deliveries Next 30 days
ETA Client Initiative · Milestone Owner Status
This week
Date TBC
Deutsche Telekom
AI Translate · Use Case + Next Steps Call
DT asked for reverse-direction translation (local languages → English) · DT yet to share expectations / updated requirements · paused through World Cup priorities, now resuming (AI SoS Aug 11) · slot not yet fixed
VS
Vishnu
● Call Scheduled
TBC
Awaiting DT
Deutsche Telekom
AI Sense · Outreach to Arindam Nath (new DT contact) — Jul 20
Commercials shared Jul 7 · Nereida moving out of Magenta Moments · Monika reached out to Arindam Jul 20 · Summer vacations — awaiting his availability
MU
Monika
● Commercial Pending
Sept 2
8 days
Emirates
Agentic Journey Demo · Dr. Najjib
Negotiated hard date (AI SoS Aug 11) · UAT live, app v2217 on TestFlight, opt-in flow complete · Octa JWT blocker open · temporary UX, labelled as such
KM
Kapileswar
● Demo Commitment
Aug 27
Thursday
Emirates
Agentic Journey MVP Demo — Internal Rehearsal
Calendar: "[Placeholder] Agentic Journey MVP Demo – Rehearsal", Thu Aug 27, 5:00–5:45 PM IST (Teams) · internal dry run ahead of the Sept 2 client demo
KM
Kapileswar
● Client Call
Deployed
Aug 11 — client testing
Jumeirah
Pulsar · GRAVTY® 2.15.0 UAT · AI-Scan On Hold
2.15.0 deployed on UAT Aug 11 — Jumeirah team now testing · AI-Scan formally On Hold in Jira (AT-112, Aug 11) · AI Recommend requirements doc with LJI
KM
Kapileswar
● UAT in Progress
Ongoing
Started Jun 22
WestJet
AI Trust · Reports Through Aug 7 · MTO/Non-PII Framework Built
3 reports to WestJet (Jun 22–Jul 8) · New models deployed on client-labelled data · Metrics comparison shared · AT-111 next
SL
Sameer
● Client Pushback
Jul 2026
2.15.1
Global Hotel Alliance
AI Trust · High Value Accrual Hold (GRAVTY® 2.15.1)
≤7,000 D$ auto-approve; >7,000 D$ held for DCC review · D$ Transfer Modeling discarded
KM
Kapileswar
● On Track
TBD
Discovery session
Shoppers Stop
AI Individualize · Sequenced Behind Execution Layer
Coupon execution + fulfilment layer is the immediate priority (Kushagra) · 6 discovery decisions open (AT-174–179) · Session with business stakeholders not yet scheduled
KM
Kapileswar
● Client Action Required
📊 Portfolio Overview 9 active clients
Client AI Modules Next Milestone ETA Waiting On Leadership Action
Deutsche Telekom
Monika Upadhayaya
AI Sense AI Translate Compass AI Retain AI Trust
AI Translate use case call + AI Sense commercial alignment
This week
AI Translate call — date TBC
⏳ Client
AI Translate: DT yet to share expectations / updated requirements — call expected this week on use case + next steps, date not yet fixed; DT's initial feedback favours reverse-direction translation (local languages → English) · Arindam Nath (new DT contact): revert on AI Sense commercial alignment · Compass: on hold — POC complete, no further action needed
AI Translate call expected this week — date not yet fixed — DT's directional feedback (local languages → English rather than the existing one-way flow) may change scope materially, and DT has not yet shared expectations or updated requirements. Treat the call as scoping; avoid committing to an approach until requirements are documented. Detail contact: Vishnu Sankar. Compass Use Case Review completed Jul 21 (8+ use cases) — confirmed proof-of-concept only, now on hold with no further next steps planned. AI Sense: Monika reached out to Arindam Nath — summer vacations delaying his availability.
Emirates
Kapileswar Mallick
Sept 2 Demo AI Individualize Ecosystem App AI Retain
Infinity Alignment Call Pending · NL Search Beta Scoping
AT-164 proposal held for 30-min alignment (Aug 17) · Sponsor URLs pending Ali (serial 31+) · AI-Ind rules pending Ali
Sept 2
Najjib demo
⏳ Client
Juggernaut: close Octa JWT auth blocker; finalise demo capability list and wireframes (Kalpak approval) before Sept 2 · Emirates: Activations to send copy updates for AI Individualize PROD go-live (Ali signed off the build Aug 24) · CCMB to confirm screen ownership for NL Search (AT-152) · Ali Lootah — sponsor URL sheet from serial 31, WIP since Aug 12 with no date · Chris Gale — response to the Infinity Discovery proposal sent Aug 21
Reward structure finalised Jul 27 (Ali Lootah): Luxury Shopping = 25% bonus; all others = 2X. Simulation on 35,446 members: 1.87M incremental bonus miles, 53% of 3.5M campaign budget. Awaiting Emirates Activations team for launch window. Agentic AI NL Search prototype Aug, EK delivery Sep.
Jumeirah
Kapileswar Mallick
AI Recommend Pulsar AI-Scan
Pulsar Deployed on UAT · Client Testing
Jumeirah One transformation — moving away from points-based programme
Deployed
Aug 11 · client testing
⏳ Client
Agentic AI MVP: Candida Goradia + Lucy Wilson to respond to Art of the Possible workshop proposal (Jul 27 email) · AI Recommend: 45-min follow-up meeting with Uzma pending
AI-Scan placed on hold Jul 24 by Candy — Jumeirah One transformation moving off points-based programme; feature will be phased out. Pulsar: GRAVTY® 2.15.0 deployed on UAT Aug 11, client informed — Jumeirah team now testing. Agentic AI MVP: Art of the Possible workshop proposed Jul 27 to Candida + Lucy — awaiting response.
Global Hotel Alliance
Kapileswar Mallick
Compass AI Trust AI Scan Ph.1 AI Sense
AI Trust · GRAVTY® 2.15.1 (Jul)
Jul 2026
2.15.1
⏳ Client
GHA — AI Scan Ph.1 eligibility mapping + pilot scope
AI Trust on track (Jul). Request GHA to confirm category/eligibility mapping to unblock AI Scan Ph.1.
Mashreq Bank
Rahul Allu
Points Adjustment
Maker-checker workflow · design analysis
Pre-PSG
Ideate stage
⏳ Juggernaut
PSG review required before the story can progress beyond Ideate · engine team to settle whether static rules are decoupled from AI Trust · Tech Design Doc (BL-127494) has no ETA
Architecture decision open — standalone module versus AI Trust integration. Design analysis must complete before build begins. This row was missing from the portfolio table entirely; added Aug 25 from existing client data.
WestJet
Sameer Lalji
AI Trust ✓
Evaluation & Reporting
Open
Solution rework
⏳ Juggernaut
Correct the search-screen approach (scalability + ancillary mapping) · re-scope bonus offers for full in-system simulation · resolve GDPR hide-vs-delete with product
No longer purely on track. AI Trust rollout is stable, but AI SoS Aug 21 records the client rejecting a search solution proposed two months earlier and refusing the rate-return approach for bonus offers in favour of full in-system simulation. Aug 20 adds 15-API-calls-per-search load, segment-level promotional rules and unresolved GDPR transaction-deletion handling.
Liverpool
Sameer Lalji
AI Individualize AI Recommend +7 modules
MVP Pilot Scoping
Epic created Jul 6 · Commercial sent — awaiting client revert
TBD
Pilot start
Internal — define pilot scope and commercial terms with Liverpool team
Epic set up in Jira (AT-122). Define MVP pilot parameters and agree commercial terms with Liverpool team to initiate delivery.
Sunrise GmbH
Monika Upadhayaya
AI Recommend
Requirements Received · Feasibility Review
Aug 6 demo call · 1.2M members · Newsletter personalisation · POC before rollout
Early 2027
Target go-live
Internal — feasibility check by Harsh & Mohiddin before timeline commitment
Requirement doc shared with Harsh and Mohiddin for feasibility review. Once complete, revert to client on timeline and implementation approach, then scope the POC.
Shoppers Stop
Kapileswar Mallick
AI Individualize
AI Sequenced Behind Execution Layer
Aug 11: coupon execution layer first · 6 discovery decisions open (AT-174–179) · Session not yet scheduled
TBD
Post-execution layer
Client — business/loyalty/campaign stakeholders to close 6 discovery decisions
Schedule the discovery session with Shoppers Stop business stakeholders to close the six Phase 1 decisions. LJI to bring a recommended starting construct rather than requiring the client to define the full solution.